Interoperability pilot schedule


Activity Plan submission: November 30th, 2015

Definition of the scenarios December 1st, 2015

Start of participation request period: December 15th, 2015


Planned kickoff date: February 9th, 2016

Development, testing and bug fixing February – June 2016

Intermediate presentation in Washington DC OGC TC March 7th -11th 2016

Planned end date: June 30th, 2016

Wrap-up and Reporting:

Technology Demonstration in a Dublin OGC TC June 20th -24th 2016

Final report submission September 2016